MissionMatters Construction Timeline

  News Updates MissionMatters
Tuesday, June 16, 2015

We now have a plan for the construction being funded by your MissionMatters pledges, and work is moving forward.

At the joint Session and Trustees meeting on Monday, June 1, the leadership of Westminster developed a plan for the construction being funded by the capital campaign:

Phase 1, replacement of the Sanctuary roof, was completed in 2014.

Phase 2, remodeling and expansion of the Camp Henry dining hall, will begin in October 2015.

Phase 3, work at 47 Jefferson Street SE, including remodeling of and improvements to the Westminster Child Development Center, the Downtown Food Pantry, and the Columbarium, will begin in spring 2016.

Because building permits could not be obtained before July 6, and because construction at 47 Jefferson is estimated to take five months, this three-phase schedule allows all construction to proceed at a reasonable pace and without impacting Westminster programs this fall.

We are now within reach of our goal to have 90 percent of the funds for the projects pledged or in hand before Phase 2 begins. The schedule also provides additional time for us to continue to seek outside grant money, such as that already pledged by the Frey Foundation.

As of June 1, 72 percent of the $2,500,000 goal has been met. With your prayerful support and pledges, we will soon have the additional 18 percent needed to begin construction of Phase 2. If you have not already made your pledge to MissionMatters, please do so as soon as possible. You can pledge online, contact the church office to have a pledge card mailed to you, or pick up a pledge card at church. Absolutely every gift matters.

Thank you for your participation, prayers, and pledges.